Shoosmiths LLP
  October 14, 2022 - Milton Keynes, England

Learning from Planning Inspector’s decision not to confirm Barking town centre CPO
  by Shoosmiths LLP

The recent decision of an Inspector not to confirm a compulsory purchase order (CPO) sought by the London Borough of Barking and Dagenham is a key reminder of the need to fully justify the use of CPO powers and provide appropriate supporting evidence.

The decision

On 4 October 2022 an Inspector decided not to confirm a compulsory purchase order (CPO) sought by the London Borough of Barking and Dagenham (Borough). The purpose of the CPO was to facilitate the regeneration of Barking town centre to provide a comprehensive mixed-use development (Scheme).

The Inspector found that there was “national policy support, regional policy drive and strong local policy” that promoted the regeneration of Barking town centre and the Scheme benefitted from outline planning permission. The evidence provided by the Borough also demonstrated “an obvious and desperate need” for the regeneration of the town centre and substantial benefits in the public interest, which resulted in the Inspector concluding that “there is an extremely compelling case” for the CPO to be confirmed.

Despite such positive comments, the Inspector ultimately decided against confirming the CPO for the following reasons:

Inadequate evidence of financial viability

The Inspector had the following concerns in relation to the viability of the Scheme:

In response to the Inspector’s concerns regarding viability, the Borough and its development partner asserted that the 2016 viability review was no longer relied upon, and that up-to-date viability information was available. However, that information could not be provided as it was commercially sensitive. The Borough also claimed that objections on the grounds of viability were not raised until at the inquiry, and thus it had no fair notice and time to respond.

This did not wash with the Inspector who noted it is the Borough’s “responsibility to provide substantive information as to the financial viability of the Scheme in light of the CPO Guidance, and to be able to defend this.” The Inspector could also “not understand why an up-to-date appraisal was not presented, even if this was redacted or subject to an independent review.” They concluded that there was insufficient substantive information to assure them that the Scheme was viable and would be delivered in a reasonable time frame.

Inadequate negotiations

Despite engaging with landowners, tenants, occupiers and leaseholders early on the process, the way in which the Borough managed negotiations with those parties was heavily criticised by the Inspector.

The Inspector noted that the Borough had failed to:

As a result of the above, the Inspector was not persuaded that the Borough had genuinely attempted to negotiate with the affected parties in line with the CPO Guidance.

Takeaways

There are some clear lessons to be learned in terms of the evidential burden and project management requirements that the Planning Inspectorate expects from acquiring authorities. It is recognised that, even with the best will in the world, issues will arise that impact the smooth running, best practice approach for effective use of CPO powers.

However, the key take home messages from the decision are as follows:

1. An acquiring authority must be able to demonstrate that adequate resources are available to implement the CPO and CPO scheme within a reasonable time frame and that there is a reasonable prospect of the CPO scheme going ahead. In terms of supporting evidence:

Note always that a well advised objector may raise issues relating to compensation considerations that are strictly the preserve of the Lands Tribunal. Whilst any debate on compensation at Inquiry will not bind the Tribunal, as the Borough found for this Scheme, a failure to provide adequate evidence that sufficient funding is available to discharge an acquiring authority’s obligations in respect of statutory compensation can result in a scheme ultimately failing and the scheme promoters facing abortive costs and wasted time.

2. A CPO is a measure of last resort, and an acquiring authority must demonstrate that reasonable steps have been taken to negotiate the acquisition of land interest by agreement. In terms of managing the negotiation process, acquiring authorities should:




Read full article at: https://www.shoosmiths.co.uk/insights/legal-updates/learning-from-planning-inspectors-decision-not-to-confirm-barking-town-centre-cpo