Businesses’ Contractual Obligation in a Time of Pandemic

Numerous sectors of the economy have been paralysed. The problem is not just closings or restricted access to arange of services, but also absence of staff due to illness, quarantine or childcare. Consequently, businesses cannot operate normally or perform their obligations on time. Alack of supplies by one company often carries over to an inability of its customers to fill their own orders. This bogs down the whole economy. We await systemic solutions allowing Polish businesses to survive. But before they arrive, it’s agood time to examine the regulations currently in force.

Coronavirus as force majeure

The coronavirus pandemic is aphenomenon which in certain circumstances may be regarded as force majeure. The term force majeure (literally, “superior force” or “higher power”) is used often in laws and contracts, but is not adefined term in Polish law. Nonetheless, force majeure is commonly recognised to mean:

  • An external event,
  • Impossible (or nearly impossible) to foresee,
  • The effects of which cannot be prevented.


These conditions must all occur together.

In contracts between businesses, force majeure is often indicated as acircumstance excluding the parties’ liability for failure to perform their obligations. The definitions used in contracts may differ in their details, but typically they take the form of general clauses, where particular events are listed only as examples, as below:

Neither party shall be liable for non-performance or improper performance of its obligations arising under this contract if caused by the occurrence of force majeure, which the parties recognise as including for example natural disaster, fire, flood, earthquake, military action, strike, blockade, interruptions in delivery of utilities (power, water), or any other circumstances or causes independent of the parties.

Of course the coronavirus pandemic is not expressly listed in such aclause, but as mentioned, the instances covered by the force majeure clause most often donot constitute afixed catalogue but only examples. Thus if contracts provide for liability, including contractual penalties, for untimely performance of services or deliveries, abusiness failing to perform its obligations as aresult of the coronavirus epidemic will be able to avoid such liability due to the lack of fault on its part.

But the circumstances where the epidemic impacts performance of contractual obligations should be capable of demonstration, to avoid situations of possible abuse. Therefore there must be acausal connection between the state of force majeure and the non-performance or improper performance of the contract. The breach must truly result from the operation of force majeure in the form of the epidemic, and not for example from the lack of due diligence required under the circumstances.

If the contract lacks provisions on force majeure, the parties may rely on general rules. Under Art. 471 of the Civil Code, the obligor is required to redress injury arising out of non-performance or improper performance of an obligation unless the breach is aconsequence of circumstances for which the obligor is not responsible.

It should be borne in mind that contractual liability is based on the principle of presumed fault. The burden of proving that abreach was due to force majeure thus rests on the party that failed to perform its obligation.

If the parties to the contract are businesses from different countries, the effects of breach of contract should be considered in light of the law governing the specific contract and the applicable provisions of international law.

Renunciation of contract, extinguishment of obligation

Contracts concluded by businesses often provide not only for non-liability or limited liability for aparty’s breach of contract due to force majeure, but also allow aparty to renounce the contract if performance by astrictly defined time is essential for the party (time is of the essence). The provisions of the contract must be carefully examined in this respect.

If aright of renunciation due to failure to make timely performance is provided for in the contract in the event of default by the other party, as arule the party can renounce the contract without designating additional time for the other party to perform. This also applies to acase where late performance by one party would be moot for the other party in light of the nature of the obligation or the aim which the party seeks to achieve through the contract, known to the other party which is in default.

But under the current circumstances, when performance of contractual obligations often proves impossible for reasons independent of the parties, it is important to note the difference between “default” [zwłoka] and “delay” [opóźnienie]. Default may be attributed to aparty that has failed to perform acontract on time for reasons for which it is responsible, i.e. dependent on the party. By contrast, delay occurs when the deadline is not met for reasons independent of the party that is late performing.

Contracts often include detailed provisions entitling one party to exercise aright of renunciation not only in the event of default, but also delay by the other party, even as aresult of force majeure, if this state of affairs continues for alength of time specified in the contract.

Thus if performance of the contract within astrictly defined time is essential for abusiness, the provisions on renunciation of the contract should be examined in particular, as well as the rules for settlements between the parties, including for advances or down payments. It should be pointed out that in the event of dissolution of the contract, adown payment made by the buyer must be refunded (not retained as the seller could dowhen the buyer defaults), and the seller’s obligation to pay double this amount (which would arise if the seller defaulted) also drops out. The same applies if the contract is not performed due to circumstances for which neither party is responsible.

The regulations also provide that if aparty obliged to perform declares that it will not perform, the other party may renounce the contract—even prior to the deadline for performance—without first setting an additional period for performance.

A party that has renounced abilateral contract is required to return to the other party all the consideration it has received from the party pursuant to the contract, and the other party is required to accept the return. Under typical circumstances (apart from force majeure), the party renouncing the contract may demand not only return of its own consideration but also redress, under general rules, of the injury arising out of failure to perform the obligation. But if non-performance of the obligation is aconsequence of circumstances for which neither party is responsible (such as the coronavirus epidemic), the rules for settlements between the parties are different, as liability for injury resulting from non-performance for reasons independent of the party must be avoided. Moreover, aparty that was supposed to perform but did not doso due to circumstances for which it is not responsible, cannot demand performance by the other party, and if it has already received that consideration it is required to return it under the provisions on unjust enrichment.

If performance by one of the parties has become only partially impossible, that party will lose aright to an appropriate portion of the other party’s consideration. But the other party may renounce the contract if partial performance would be moot for the other party in light of the nature of the obligation or the aim which the party seeks to achieve through the contract, known to the other party. In other words, if partial performance would serve no purpose for the other party, it may renounce the contract in its entirety.

If as aresult of renunciation of the contract the parties are to return their mutual consideration, each of them has aright to retain the consideration received until the other party tenders the return of the consideration it has received or secures the claim for return.

Apart from the right to renounce the contract, under Civil Code Art. 475 §1 if performance has become impossible due to circumstances for which the obligor is not responsible, the obligation is extinguished. Impossibility of performance resulting in extinguishment of the obligation covers situations where after the obligation arises, there is astate of complete, lasting and objective inability for the party to act in the manner provided for in the substance of the obligation, and not just atemporary difficulty in performing.

Clause on extraordinary change in circumstances

If the parties cannot reach agreement, they can rely on the clause on extraordinary change in circumstances (rebus sic stantibus), set forth in Art. 3571 of the Civil Code. This regulation provides that if due to an extraordinary change in circumstances, fulfilment of performance would involve excessive difficulty or expose one of the parties to aglaring loss which the parties did not foresee when concluding the contract, the court may, after weighing the interests of the parties, and in accordance with principles of social coexistence, designate the manner of performance of the obligation or the amount of the consideration, or even rule that the contract is dissolved. When dissolving the contract, the court may, if necessary, rule on the settlements between the parties, guided by the same general principles.

The grounds for this clause could be analysed more extensively, but in the existing situation its application is limited not so much by legal reasons as practical considerations. What is needed now is immediate solutions to quickly stabilise businesses’ current operations. Considering that the courts have also limited their activity, taking cases like this into litigation at the same time as the problem becomes widespread would offer neither afast nor an effective solution, given the tempo of changes in circumstances and mutual business relationships.

What can businesses doin the time of the coronavirus?

Until new regulations and aprotective package for business are adopted, businesses should respond on an ongoing basis through mutual concessions allowing everyone to make it through the crisis. Because delays in performing contracts are global, businesses should consider renouncing their existing contracts only as afinal resort.

Undoubtedly amore practical solution is renegotiation of contracts, in particular commercial contracts or contracts for performance of certain services. It would be worthwhile to take up renegotiations now, even though the situation is hard to predict, in order to regulate the parties’ mutual obligations not only for the future (after the epidemic ends) but first and foremost to stabilise the current situation. Negotiations may involve the possibility of performing obligations, changes in deadlines, spreading payments out over time, and also mutual agreement on repayment of currently outstanding amounts in order to avoid any loss of financial liquidity on the part of businesses as well as their customers and suppliers. In these tough times, communications and solidarity are vital in the interconnected world of business. After all, if acustomer or supplier fails, it can also threaten one’s own business.

The Ministry of Development has announced that it is drafting aspecial act introducing comprehensive support for businesses whose operations are impacted by the spread of Covid-19. The specifics of the proposal are not yet known, but the bill is supposed to be presented to the Sejm on 25 March 2020 and take effect on 1 April 2020. We write more on this topic in the article “Coronavirus: Shielding package for business.”

 

Source: www.inprinciple.pl