Discharging Cargo from Ships that are Under Arrest
July, 2020 - Rajasingam Gothandapani
A ship may be arrested in Malaysia as long as the claim of the arresting party falls under any of the provisions of Section 20(2) and Section 21 of the Supreme Court Act 1981 of England and Wales.
Any party that wants to arrest a ship in Malaysia must strictly comply with Order 70 of the Rules of Court 2012 (the ROC 2012), which governs admiralty proceedings in the High Court.
On the arrest of a ship, it will not be allowed to work without the sheriff's express permission. This means that the loading and unloading of cargo is not allowed without the sheriff's prior approval.
If the ship has commenced loading before the arrest takes place, the sheriff or assistant sheriff will direct the master of the ship to cease all cargo loading operations immediately after the execution of the warrant of arrest.
In the event that the ship is under arrest, but the cargo is not, any party entitled to immediate possession of the cargo (the cargo interest) may have the cargo discharged from the ship.
Order 70, Rule 12(8) of the ROC 2012 provides that where a ship is under arrest but the cargo on board is not, the cargo interest that wishes to discharge the cargo may, without being made parties in the action, request the sheriff or assistant sheriff to authorise steps to enable the cargo to be discharged.
Under Order 70 rule 12(9) of the ROC 2012, if the sheriff or assistant sheriff considers a request to be reasonable and the cargo interest gives a written undertaking to pay the sheriff 's fees and expenses, the sheriff or the assistant sheriff may apply to the courts for an order to permit the discharge of the cargo. Alternatively, pursuant to Order 70, Rule 12(10) of the ROC 2012, the cargo interest that is unable or unwilling to provide said undertaking may intervene to be made parties to the action and apply to the courts for an order to discharge the cargo from the ship and directions as to the sheriff's fees and expenses in relation to the cargo's discharge and storage.
Order 70, Rule 16(1) of the ROC 2012 provides for cargo interests to apply to the courts for leave to intervene in the action. The leave application will be madeex parteby way of notice of application supported by an affidavit showing the applicant's interest in the cargo on board the ship that is under arrest and against which the action has been brought.
According to Order 70, Rule 16(3) of the ROC 2012, where leave has been granted by the courts to the cargo interest as the intervener, the cargo interest will thereupon become a party to the action and enter an appearance therein in the registry within the period specified in the court order for granting the leave.
In the event that a ship is under arrest and the cargo laden on board is not, the intervener or cargo interest that asserts rights over the cargo would have to offload the cargo at its and not at the sheriff's expense. InThe SeaUrchin[2014] SGHC 24, the Singapore High Court held as follows:
[30] In the present case, the Vessel, and not its cargo, was under arrest.Theintervener who asserts rights over the cargo would have to off-loadthe cargo at its expense, and not at the Sheriff's expense. This would bethe position unless the equities of the case justify treating the costs ofdischarge as Sheriff's expenses (see The Nagasaki Spirit [1994] 2 SLR(R) 165at [30])…
[34]… Just asthe costs of discharge of cargo do not fall automaticallyunder Sheriff's expenses, transhipment expenses for the same reasons statedabove should not be treated as Sheriff's expenses to be paid out from the saleproceeds. In the final analysis,such costs are, in principle, claims foreach of the contract of carriage against the vessel owners and/or thecharterers.(Emphasis added.)
The English case ofThe Jogoo[1981] 1 WLR 1376 also provides that "in the event of a contract of carriage not being completed by ship-owners the cargo-owners should pay for the removal of their own cargo and then claim against the ship-owners for the damage suffered".
Malaysian law permits the discharge of cargo on board a ship that is under arrest when the cargo itself is not. The discharge of the cargo will be at the expense of the intervener that asserts its rights over the cargo – namely, the cargo interest. Applications of this nature are usually filed and heard on an urgent basis by way of a certificate of urgency.
For further information on this topic please contactRajasingam Gothandapaniat Shearn Delamore & Co by telephone (+603 20272911) or email ([email protected]). The Shearn Delamore & Co website can be accessed atwww.shearndelamore.com.